What is Earned Value Management (EVM) and name its primary metrics (PV, EV, AC, CPI, SPI).

Study for the CMPM Exam. Utilize our multiple-choice questions and flashcards, each featuring hints and explanations. Prepare for success!

Multiple Choice

What is Earned Value Management (EVM) and name its primary metrics (PV, EV, AC, CPI, SPI).

Explanation:
Earned Value Management is a performance measurement technique that brings together what was planned to be done, what has actually been done, and what it has cost to gauge how the project is performing in terms of scope, schedule, and cost. Planned Value represents the budgeted cost for the work scheduled to be completed by now; Earned Value is the budgeted cost for the work actually completed; Actual Cost is the real money spent to perform the work. From these, two key indicators come out: Cost Performance Index (CPI) = EV / AC, which shows cost efficiency, and Schedule Performance Index (SPI) = EV / PV, which shows schedule efficiency. For example, if PV is 1000, EV is 900, and AC is 1100, then CPI is 0.82 (cost overrun) and SPI is 0.90 (behind schedule). The other choices describe frameworks that don’t capture this integrated measurement approach, whereas EVM specifically uses planned value, earned value, and actual cost with the CPI and SPI ratios to assess performance.

Earned Value Management is a performance measurement technique that brings together what was planned to be done, what has actually been done, and what it has cost to gauge how the project is performing in terms of scope, schedule, and cost. Planned Value represents the budgeted cost for the work scheduled to be completed by now; Earned Value is the budgeted cost for the work actually completed; Actual Cost is the real money spent to perform the work. From these, two key indicators come out: Cost Performance Index (CPI) = EV / AC, which shows cost efficiency, and Schedule Performance Index (SPI) = EV / PV, which shows schedule efficiency. For example, if PV is 1000, EV is 900, and AC is 1100, then CPI is 0.82 (cost overrun) and SPI is 0.90 (behind schedule). The other choices describe frameworks that don’t capture this integrated measurement approach, whereas EVM specifically uses planned value, earned value, and actual cost with the CPI and SPI ratios to assess performance.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy