What is resource leveling and what's a potential downside?

Study for the CMPM Exam. Utilize our multiple-choice questions and flashcards, each featuring hints and explanations. Prepare for success!

Multiple Choice

What is resource leveling and what's a potential downside?

Explanation:
Resource leveling focuses on smoothing the workload when resources are overallocated by adjusting task timings within available slack, so that resources aren’t stretched too thin. This often means delaying or rescheduling non-critical tasks to balance demand over time, rather than speeding up work with extra resources. The key downside is that this can lengthen the overall project duration and reduce schedule flexibility, since work may be pushed into later periods and milestones or the critical path can shift as a result.

Resource leveling focuses on smoothing the workload when resources are overallocated by adjusting task timings within available slack, so that resources aren’t stretched too thin. This often means delaying or rescheduling non-critical tasks to balance demand over time, rather than speeding up work with extra resources. The key downside is that this can lengthen the overall project duration and reduce schedule flexibility, since work may be pushed into later periods and milestones or the critical path can shift as a result.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy