Which statement best contrasts agile and plan-driven project management?

Study for the CMPM Exam. Utilize our multiple-choice questions and flashcards, each featuring hints and explanations. Prepare for success!

Multiple Choice

Which statement best contrasts agile and plan-driven project management?

Explanation:
The main idea being tested is how agile contrasts with plan-driven approaches in handling planning and change. Agile works in short iterations, delivering increments and adjusting plans as you learn, so requirements can evolve and the plan adapts. Plan-driven, often described by a waterfall mindset, relies on upfront, fixed plans and a linear sequence of phases, with the scope, schedule, and budget established early and changes treated as disruptive. The statement that agile embraces change with iterative delivery and adaptive planning while plan-driven relies on upfront, fixed plans and sequential phases captures this distinction most accurately. The other options mischaracterize agile as avoiding change or misstate how plan-driven and agile manage delivery and scope.

The main idea being tested is how agile contrasts with plan-driven approaches in handling planning and change. Agile works in short iterations, delivering increments and adjusting plans as you learn, so requirements can evolve and the plan adapts. Plan-driven, often described by a waterfall mindset, relies on upfront, fixed plans and a linear sequence of phases, with the scope, schedule, and budget established early and changes treated as disruptive. The statement that agile embraces change with iterative delivery and adaptive planning while plan-driven relies on upfront, fixed plans and sequential phases captures this distinction most accurately. The other options mischaracterize agile as avoiding change or misstate how plan-driven and agile manage delivery and scope.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy