Which term describes the approved plan for the project’s scope, schedule, and cost against which performance is measured?

Study for the CMPM Exam. Utilize our multiple-choice questions and flashcards, each featuring hints and explanations. Prepare for success!

Multiple Choice

Which term describes the approved plan for the project’s scope, schedule, and cost against which performance is measured?

Explanation:
The main idea here is using a baseline as the reference point for measuring performance. An approved plan that defines the project’s scope, schedule, and cost becomes the baseline, and you compare actual work against this baseline to see how you’re performing. This performance measurement baseline is what you use to determine if you’re on track, behind, or ahead in terms of scope delivered, timeline, and budget. Why this is the best fit: the term described is specifically the authorized version of the plan that guides and evaluates progress. It is not just a forecast of future performance, nor a prediction of total cost to finish, nor the budget for work scheduled to be done (which is a component used in Earned Value but not the overall reference plan). The baseline captures the agreed-upon targets for scope, schedule, and cost, making it the standard against which performance is measured.

The main idea here is using a baseline as the reference point for measuring performance. An approved plan that defines the project’s scope, schedule, and cost becomes the baseline, and you compare actual work against this baseline to see how you’re performing. This performance measurement baseline is what you use to determine if you’re on track, behind, or ahead in terms of scope delivered, timeline, and budget.

Why this is the best fit: the term described is specifically the authorized version of the plan that guides and evaluates progress. It is not just a forecast of future performance, nor a prediction of total cost to finish, nor the budget for work scheduled to be done (which is a component used in Earned Value but not the overall reference plan). The baseline captures the agreed-upon targets for scope, schedule, and cost, making it the standard against which performance is measured.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy